How to read a quarterly progress report
Written by Royal Vente's research team (AI), reviewed by Nishchal Gaba, checked on .
Next check by 9 January 2027 · 9 minute read
In short
- A registered project must report its progress to HARERA every quarter, in public.
- The report shows what is booked, what is built, which approvals are in and what is pending.
- Read it against the completion date the developer declared at registration.
When you buy a home that isn't built yet, you are trusting the developer's timeline. In Haryana, the promoter of every registered project must tell the regulator, every quarter and in public, how far the work has got. This guide shows you where to find those reports and how to read them.
What the law asks for
Section 11(1) of the RERA Act says the promoter must keep a web page for the project on the authority's website, open to the public, and update these every quarter:[1]
- the number and types of apartments or plots booked;
- the number of garages booked;
- the approvals taken, and the approvals still pending after the commencement certificate;
- the status of the project.
Haryana's rules add detail. Within fifteen days of the end of each quarter, the promoter uploads the bookings, the parking booked, the status of construction of each building with photographs, the status of internal infrastructure and common areas with photographs, and the approvals received, applied for and still to be applied for.[2] HARERA Gurugram's regulations set the format of the report, called the quarterly progress report or QPR, and ask for it to reach the authority before the 15th of the month after the quarter ends.[3]
Find the reports
- Open HARERA Gurugram's Registered Projects list and find the project. Our guide to the list explains how.
- In the View Quarterly Progress column, open View. A table lists each quarter with its number, start date and end date, such as “1 of 2021”, and a View Details button.[5]
- If the column says “QPR not Uploaded” instead, the list shows no report for that project. On the day we read it, 173 of the 1,082 projects on the list showed those words.[5]
What's in a report
The regulations set out the report in parts.[3]
| Part | What it covers |
|---|---|
| Particulars | The project, its registration and how long it is valid, and the quarter reported. |
| Part A: physical progress | The number of plots and homes completed, by block and tower; the estimated and actual percentage of work at each stage of each tower; and the infrastructure and services. |
| Part B: financial progress | The quarter's estimated spending, where the money came from, and the net cash flow. |
| Part C: miscellaneous | Agents who booked units, advertisements issued, legal cases, sales, approvals received, expired and applied for, money collected, withdrawals from the project account, and dues to the government. |
| Annexures | Photographs of the site, approvals, and the latest marketing material and advertisement. |
With each report come certificates from an architect, an engineer and a chartered accountant, each in practice, that money taken out of the project's separate account matches the percentage of the project completed.[3, 4]
About the format
This describes the official form. On the portal, each quarter opens through a button that sends a form, which we don't do, so a report on screen may be laid out differently.
The separate account, in one paragraph
Under section 4(2)(l)(D) of the Act, seventy per cent of the money a promoter collects from buyers for a project goes into a separate account in a scheduled bank, to cover the cost of construction and the land, and is used only for that. Money can come out only in proportion to the work completed, after an engineer, an architect and a chartered accountant certify it, and the accounts must be audited within six months of the end of each financial year.[1] The quarterly report is where those withdrawals show up.
How to read it: six checks
- Progress against time. Set the actual percentages in Part A against the time left until the registration's validity date, which is the completion period the promoter declared. A large gap is a question to ask, not proof of a delay.
- Missing quarters. Count the quarters since registration and see that each one has a report. Our own rule: we don't show a project whose reports are missing for two quarters in a row with no reason on record. See how we check.
- Estimated against actual. Each report gives both. If actual work trails the estimate quarter after quarter, ask why, and what the plan is now.
- Your tower. Progress is reported tower by tower. Find the one you're buying in, not the project's average.
- Approvals. Part C lists approvals received, expired and applied for. An approval that has expired, or is still pending, is a question to ask.
- Money and photographs. Withdrawals and collections should move with the work. The photographs should show the stage the report claims.
A promoter that breaks the Act, the rules or the regulations, for example by not filing, can be fined up to five per cent of the estimated cost of the project under section 61.[1]
What a report can't tell you
A quarterly report is the promoter's own account, with professionals' certificates. HARERA Gurugram has made regulations for a compliance cell, whose work includes checking on site that the spending shown in reports matches the progress there and the architect's certificate.[6] Even so, a report is not a promise of a completion date, and nothing replaces seeing the site, yourself or through someone you trust.
Sources
- The Real Estate (Regulation and Development) Act, 2016, sections 4(2)(l)(D), 11(1) and 61 (Gazette text). haryanarera.gov.in/images/ReraActs2017.pdf. Read on 9 October 2026.
- Haryana Real Estate (Regulation and Development) Rules, 2017, rule 14. haryanarera.gov.in/regulations/ReraRules2017.pdf. Read on 9 October 2026.
- HARERA Gurugram (Quarterly Progress Report) Regulations, 2018, No. 12/RERA GGM Regulations 2018, substituted text of 21 May 2019, with Form QPR-I. haryanarera.gov.in/regulations/quarterly.pdf. Read on 9 October 2026.
- HARERA Gurugram (Quarterly Progress Report) Regulations, 2018, original text of 5 December 2018. haryanarera.gov.in/regulations/Quarterly_Progress_ReportGURUGRAMRegulations2018.pdf. Read on 9 October 2026.
- HARERA Gurugram, Registered Projects. haryanarera.gov.in/admincontrol/registered_projects/2. Read on 9 October 2026.
- HARERA Gurugram regulations on a compliance cell for audit of annual statements and QPRs, No. 27/RERA GGM Regulations 2024. haryanarera.gov.in/regulations/Establishment_of_compliance%20cell_for_Audit_of_Annual_statemens_%20and_QPR_of_projects_Regulations_2024_grg.pdf. Read on 9 October 2026.
General information, not legal or tax advice.
This guide explains public records and the law as we read them on the date above. It doesn't name or assess any project, and it doesn't replace your own lawyer or CA. Found a mistake? Tell us.
Related guides
See section 3 of the sample fileCheck a projectLegal and paperwork
Check any Gurugram project on HARERA in ten minutes
Is this project really registered, and is its registration still valid?
Checked on 8 minute read
Check a projectLegal and paperwork
What a DTCP licence tells you, and how to look one up
Who holds the land, and is it licensed for this project?
Checked on 8 minute read